Rehab work begins on Harrison St. bridge

(August 22, 2025) Watch for changing traffic control on the Harrison St. bridge over Duck Creek the week of August 25. Two lanes of travel should be maintained. The Duck Creek Recreational Trail will remain detoured until rehabilitation is complete. The Iowa Department of Transportation estimates work will be complete in December.
(April 4, 2025) The Iowa Department of Transportation will begin rehabilitation work on the Harrison St. bridge over Duck Creek on April 7, 2025.
During construction, travel will be limited to two lanes lanes between W 35th and W 32nd Streets.
The Duck Creek Recreational Trail under the bridge will be closed. Runners and cyclists can use the new temporary connection on the street level, with the help of a pedestrian signal to cross Harrison St.
The Iowa DOT estimates work will be complete in November.
Work Zone Details and Detours