Description/Goal

This project is included in the Iowa DNR Consent Order. It will abandon large sections of the 1930's sanitary sewer while rehabilitating certain section connected to the 1970's interceptor for continued use.

Current Update

The construction contract has been awarded to Langman Construction.  Work is expected to begin by the end of the calendar year, once final construction phasing has been determined.  

Previous Status

The preliminary design of the project has been reviewed and approved by the Iowa Department of Natural Resources. The project is currently out to bid; it is scheduled to close on August 6th.

Operational Pillar: Sustainable Infrastructure

Council Goal: Improve Infrastructure

Project Leader: Schadt/Doran/Guy

Target Completion: 4Q-21

Progress: 30%